NVIDIA H200 shipments delayed to Q3  · BREAKING: Microsoft confirms 3GW data centre expansion in Asia-Pacific ·  AWS announces new sovereign cloud regions in India and UAE  · Arm-based servers now 24% of hyperscale deployments ·  EU AI Act enforcement enters phase two  · Global data centre investment hits $612B in 2026 ·  TSMC Arizona yields improve to 68% on 3nm process  · OpenAI valuation reaches $400B after latest funding round ·  NVIDIA H200 shipments delayed to Q3  · BREAKING: Microsoft confirms 3GW data centre expansion in Asia-Pacific ·  AWS announces new sovereign cloud regions in India and UAE  · Arm-based servers now 24% of hyperscale deployments ·  EU AI Act enforcement enters phase two  · Global data centre investment hits $612B in 2026
NVIDIA H200 shipments delayed to Q3  · BREAKING: Microsoft confirms 3GW data centre expansion in Asia-Pacific ·  AWS announces new sovereign cloud regions in India and UAE  · Arm-based servers now 24% of hyperscale deployments ·  EU AI Act enforcement enters phase two  · Global data centre investment hits $612B in 2026 ·  TSMC Arizona yields improve to 68% on 3nm process  · OpenAI valuation reaches $400B after latest funding round ·  NVIDIA H200 shipments delayed to Q3  · BREAKING: Microsoft confirms 3GW data centre expansion in Asia-Pacific ·  AWS announces new sovereign cloud regions in India and UAE  · Arm-based servers now 24% of hyperscale deployments ·  EU AI Act enforcement enters phase two  · Global data centre investment hits $612B in 2026

HUMAIN and DataVolt Advance 100MW AI Data Center at Oxagon

HUMAIN and DataVolt are moving a major piece of Saudi Arabia’s AI infrastructure strategy from announcement to construction, with a

Share
Humain

HUMAIN and DataVolt are moving a major piece of Saudi Arabia’s AI infrastructure strategy from announcement to construction, with a 100MW development at Oxagon, NEOM’s industrial city on the Red Sea coast. The companies announced an expanded partnership at LEAP to jointly develop 100MW within the 360MW first phase of DataVolt’s planned AI data center campus. Construction is already underway, giving the project a more consequential status than another capacity target sitting on an infrastructure roadmap. The first 100MW is expected to become available in 2028.

100MW Becomes the First Delivery Test

The development will sit inside DataVolt’s 360MW first phase, which itself forms part of a much larger 1.5GW Oxagon campus. That hierarchy matters because the immediate 100MW build provides a tangible delivery milestone while the broader campus remains a longer-term expansion opportunity. DataVolt expects the first phase to support large-scale AI workloads from domestic and international customers, rather than positioning the facility solely as a conventional cloud data center. The project therefore places physical compute capacity at the center of HUMAIN’s broader ambition to build an AI stack in Saudi Arabia.

The facility is being designed around the unusually demanding power and thermal characteristics of accelerated computing. Renewable energy sources, innovative cooling technologies and high-performance computing clusters are expected to work together to support AI and cloud workloads at scale. HUMAIN brings capabilities across the AI stack, while DataVolt contributes experience spanning development, financing, delivery and operations of large digital infrastructure projects. That combination makes the partnership less about simply securing data center space and more about connecting AI platforms and workloads with infrastructure capable of running them. 

HUMAIN Links AI Ambition to Physical Compute

Tareq Amin, CEO of HUMAIN, framed the project around execution rather than another high-level AI commitment. “AI ambition only matters when you can turn it into infrastructure, compute and capacity that customers can use. That is what this partnership with DataVolt is about. Construction is underway, 100MW is moving forward, and we are building with the speed and scale that the next era of AI demands.”

For DataVolt, the groundbreaking also establishes the construction start of the wider 360MW first phase within its planned 1.5GW campus. The company is building on an infrastructure pipeline spanning Saudi Arabia and Central Asia, alongside experience structuring capital-intensive digital infrastructure projects. Rajit Nanda, CEO of DataVolt, emphasized execution across the entire infrastructure chain, from power and engineering through construction and operations. His statement also underscores the distinction between announcing AI capacity and actually delivering the infrastructure required to operate it.

“AI infrastructure at this scale demands more than capital and capacity, but disciplined execution, from power and engineering through construction and operations. Our partnership with HUMAIN brings together our complementary capabilities with a clear focus on delivery and bringing world class digital infrastructure capacity to the Kingdom. Breaking ground at Oxagon is an important milestone as we move forward with the first 360MW phase and build the infrastructure required to support AI compute at scale.”

Oxagon’s Infrastructure Shapes the Economics

The site offers several characteristics that directly address the constraints increasingly shaping AI infrastructure projects. Oxagon provides pre-zoned industrial land, access to energy resources at scale and subsea cable connectivity toward Europe and Africa, giving the campus a potential advantage in development speed and network reach. Those inputs matter because AI infrastructure economics increasingly depend on securing power, land, connectivity and operating efficiency alongside compute hardware. Meanwhile, the location gives the project a route into international digital infrastructure markets while supporting Saudi Arabia’s domestic AI ambitions.

Eng. Aiman Al-Mudaifer, Managing Director and Chief Executive Office of NEOM, described the development as evidence of the industrial ecosystem forming around Oxagon. “Breaking ground on the HUMAIN and DataVolt project is an important demonstration of the industrial ecosystem taking shape at Oxagon. The ability to secure the power, land and connectivity needed to grow is becoming critical to the economics of AI. As progress on the first phase of DataVolt’s AI campus accelerates, Oxagon is bringing these advantages together to create a strong proposition for companies building the infrastructure required for the next generation of AI.”

The Bigger Bet Is 1.5GW

The 100MW project ultimately serves as the first meaningful execution point within DataVolt’s much larger 1.5GW Oxagon vision. The first phase is planned at 360MW, with the initial 100MW expected to be ready in 2028 and designed for high-density AI and cloud workloads. The scale reflects how rapidly infrastructure requirements are changing as AI systems demand increasingly powerful computing, greater power density and more sophisticated cooling. The project also gives Saudi Arabia a physical platform from which AI compute can move from strategic ambition toward deployable capacity.

[simple-author-box]

More from AI Infrastructure

SLB is making one of its clearest moves yet into the data center economy,

Kyocera Ventures, the investment arm of Japan’s Kyocera Corporation, has made a strategic investment

ST Telemedia Global Data Centres (STTGDC) has completed its acquisition by a consortium led

COMPUTE WEEKLY

The briefing that 40,000+ tech leaders read every Monday. Sharp, fast, essential.

Great! We’ve received your information.

Building an AI Startup Without Owning GPUs

Not owning GPUs has become the default, deliberate strategy for building an AI company — not a compromise founders accept reluctantly. H100 rental rates fell 64-75% in fifteen months, a dense ecosystem of neoclouds and inference-as-a-service providers now lets startups skip infrastructure entirely, and credit programs can fund a company’s first year before a founder writes a check
Most Read

A data center master plan can establish a defined technical basis before all future

A transformer can leave a refurbishment shop looking almost indistinguishable from a new unit,

Why Samsung Is Taking AI Infrastructure Offshore AI infrastructure now faces a practical challenge

AI infrastructure decisions for high-density deployments increasingly involve what happens after electricity enters the

Demand is broadening across enterprise workloads APAC’s infrastructure story is changing in ways that

Disruptor Spotlight

Cerebras Systems

The chip that makes Nvidia nervous. Cerebras’ Wafer Scale Engine is rewriting the rules of AI inference at scale.
Faster
0 x
YoY Revenue
0 x
Transistors
0 T
Market Pulse
MSFT
+1.02%
NVDA
+0.66%
AMZN
-0.078%
AMD
-6.95%
TSMC
-2.98%
Indicative only · Not financial advice
Upcoming Events
SEP
The AI Infrastructure Race (India)
WEBINAR · ONLINE
The AI Infrastructure Race: Won on Power, Land and Trust — Not Capital
MAY
0
AI Infrastructure Summit
DUBAI · IN PERSON
MEA’s premier AI infrastructure event.
JUN
0 0
Compute Forecast Summit
SINGAPORE · IN PERSON
Our flagship APAC event. Early bird open.
Latest Moves
Live
ecolab
Ecolab Deepens Cooling Strategy With $4.75B CoolIT Acquisition
Ecolab is making one of its biggest moves yet into AI infrastructure after completing its $4.75 billion acquisition of liquid cooling specialist CoolIT Systems
Pure DC AVK Europe data center microgrid Dublin 110MW AI infrastructure Ireland 2026
Pure DC and AVK Deploy Europe’s First 110 MW Data Center Microgrid in Dublin
The Pure DC Dublin microgrid has made history as Europe’s first large-scale on-site data center microgrid, launched in partnership with power solutions provider AVK at Pure DC’s campus in Ireland.
Pace Digitek
Pace Digitek Partners With MEGMEET to Expand AI Data Center Power Business
India’s AI infrastructure ecosystem continues to mature as domestic technology manufacturers move beyond traditional telecommunications and industrial markets toward high-growth digital infrastructure opportunities
Follow Compute Forecast
11K followers
1200 followers
Companies to Watch
CW
CoreWeave
Neo Cloud · $19B · IPO Watch
CB
Cerebras Systems
AI Hardware · $4.25B · Pre-IPO
G42
G42
Sovereign AI · Abu Dhabi
H
Humain
Saudi AI · $40B Fund
Latest Podcast
AI Capex, Cloud Margins & the Nuclear Bet
48 MIN · 25 APR 2026

HUMAIN and DataVolt Advance 100MW AI Data Center at Oxagon

HUMAIN and DataVolt are moving a major piece of Saudi Arabia’s AI infrastructure strategy from announcement to construction, with a

Share
Humain
4
847 SHARES

0
SHARES

[simple-author-box]

More from AI Infrastructure

A data center master plan can establish a defined technical basis before all future

A transformer can leave a refurbishment shop looking almost indistinguishable from a new unit,

Why Samsung Is Taking AI Infrastructure Offshore AI infrastructure now faces a practical challenge

AI infrastructure decisions for high-density deployments increasingly involve what happens after electricity enters the

COMPUTE WEEKLY

The briefing that 40,000+ tech leaders read every Monday. Sharp, fast, essential.

Great! We’ve received your information.

Global AI Infrastructure Outlook 2026

The briefing that 40,000+ tech leaders read every Monday. Sharp, fast, essential.
Download Free
Most Read

A data center master plan can establish a defined technical basis before all future

A transformer can leave a refurbishment shop looking almost indistinguishable from a new unit,

Why Samsung Is Taking AI Infrastructure Offshore AI infrastructure now faces a practical challenge

AI infrastructure decisions for high-density deployments increasingly involve what happens after electricity enters the

Demand is broadening across enterprise workloads APAC’s infrastructure story is changing in ways that

Disruptor Spotlight

Cerebras Systems

The chip that makes Nvidia nervous. Cerebras’ Wafer Scale Engine is rewriting the rules of AI inference at scale.
Faster
0 x
YoY Revenue
0 x
Transistors
0 T
Market Pulse
NVDA
$924.60
+2.4%
MSFT
$421.30
+1.1%
AMZN
$192.80
-0.6%
NVDA
$924.60
+2.4%
NVDA
$924.60
+2.4%
Indicative only · Not financial advice
Upcoming Events
MAY
0 0
DCD Global — London
LONDON · IN PERSON
World’s largest DC event. CF is media partner.
MAY
0
AI Infrastructure Summit
DUBAI · IN PERSON
MEA’s premier AI infrastructure event.
JUN
0 0

Compute Forecast Summit

SINGAPORE · IN PERSON
Our flagship APAC event. Early bird open.
Latest Moves
  • Live
Sam Altman
OpenAI appoints new Chief Infrastructure Officer to lead $100B DC programme
27 APR · OPENAI
Sam Altman
OpenAI appoints new Chief Infrastructure Officer to lead $100B DC programme
27 APR · OPENAI
Sam Altman
OpenAI appoints new Chief Infrastructure Officer to lead $100B DC programme
27 APR · OPENAI
Follow Compute Forecast
18.4K followers
12.1K followers
9.3K subscribers
41 episodes
Companies to Watch
CW
CoreWeave
Neo Cloud · $19B · IPO Watch
CB
Cerebras Systems
AI Hardware · $4.25B · Pre-IPO
G42
G42
Sovereign AI · Abu Dhabi
CW
Humain
Saudi AI · $40B Fund
Latest Podcast
AI Capex, Cloud Margins & the Nuclear Bet
48 MIN · 25 APR 2026
Scroll to Top
Seraphinite AcceleratorOptimized by Seraphinite Accelerator
Turns on site high speed to be attractive for people and search engines.